Load bank testing

Load bank test procedure and requirements

A UPS load bank test is a sequence of transfers, load steps and checks written down before anyone arrives on site. This page sets out what the site must provide and the procedure step by step, as a UPS maker publishes it.

Key facts

What must the site provide before a load bank test?

The site must be able to carry the extra load, give the load bank somewhere to shed its heat, and have a qualified person make the connections. In practice that means:

Load bank test power pathThe supply feeds the UPS rectifier and inverter; the inverter output feeds the load bank; the critical load is carried on the maintenance bypass from the supply, outside the UPS.SupplyUPS under testRectifierInverterBatteryLoad bankTest loadMaintenance bypassCritical load
During the test the critical load runs on the maintenance bypass (dashed) and the load bank is connected to the UPS output, so the test load never reaches the protected equipment.

What happens at each stage, and what is recorded?

What happensWhat is recorded
Infrastructure check: the site can carry the critical load and the test load togetherThe check, and the approval to proceed
Critical load transferred to bypass, then to maintenance bypassTransfer times and any alarms
UPS modules shut down; lockout tag-outWho applied the locks
Load bank connected to the UPS output by the electricianConnection points and cable route
UPS restarted and transferred to normal, on the load bankUPS status and alarm log
Load at 50% for one hourVoltage, current, regulation; infrared and power-quality readings in a performance test
Load at 100% for 3 hoursThe same readings, at full load
Battery discharge by opening the rectifier input, up to 4 minutesUPS parameters during the discharge; battery cabinet scan
Rectifier input restored; batteries rechargeRecharge behaviour
Transfers to bypass and back, repeated three timesWhether each transfer was clean
Load removed, load bank isolated and disconnected, locks removedCompletion of each step
Critical load returned from maintenance bypass to normalFinal UPS status; the report follows

Who signs off before the load is applied?

The electrician and the site's own personnel, after the infrastructure check. Eaton's method makes this approval its second step: nothing is transferred until the people responsible for the site agree that it can carry both loads. The written method also names who can stop the test and what readings would make them stop it.

Why is the transfer repeated?

Because a single clean transfer proves little. After the load steps and the battery discharge, Eaton's method transfers the UPS to bypass and back to normal and repeats the transfer three times, under the test load, before the load bank is removed. A transfer that fails or misbehaves on the bench is far cheaper to find than one that fails during an outage.

How long should the site plan for?

A full working day for the test itself. The load steps alone take one hour at 50% and 3 hours at 100%; add the transfers to and from maintenance bypass, the connections, the battery discharge of up to 4 minutes and its recharge, and the repeated transfers. Some UPS need longer steps or more of them: the maker's method for that model decides.

What does a performance test add?

Thermal and power-quality readings. Eaton's performance-test scope runs the same load steps with an infrared scan of the UPS and battery cabinets at each step and during the battery discharge, and a power-quality meter on the UPS output recording voltages, currents and harmonic content. Hot spots are recorded with their actual temperatures, and thermographs go into the written report.

What happens to protection during the test?

The critical load runs on maintenance bypass, which means utility power without UPS conditioning. On some UPS the batteries are not available in maintenance bypass, as Schneider Electric notes for the Galaxy VS. The test window is chosen with that in mind: away from known utility work and storms, and with the generator ready.

Related pages

Questions

Who writes the test procedure?

The procedure follows the UPS maker's method for that model; it is written and agreed with the site before the visit, including the stop criteria and who signs off each step.

Does the test need an electrician?

Yes. In Eaton's method a certified electrician makes the connections from the load bank to the UPS before testing and removes them afterwards.

How much cable does a load bank need?

Enough to reach a place where its heat can be rejected safely. Eaton's scope supplies 50 feet and adds more on request.

What if a reading is out of range?

The test stops at the step where it happened, the load returns to a safe state as the written method sets out, and the finding goes in the report with what it needs.

Sources, checked 2026-10-04:

Need a UPS serviced, tested or replaced?

Tell us the site, the UPS and the timing. We reply and quote within 4 business hours, or call 1 (438) 800-0382

Request a quote →

Brand names are trademarks of their owners and are used only to identify the equipment we service. We are not the manufacturer and are not affiliated with it.

Call 1 (438) 800-0382Request a quote