Commissioning proves that a newly installed UPS works as designed before it carries the critical load: start-up to the maker's procedure, functional checks of every operating mode, a load test, battery checks, and a handover file with the results.
It proves that the installed system, not just the UPS on its own, does what the design says: it starts, transfers, carries the load at its rating, runs on battery, returns to normal, and alarms when it should. ASCO's load bank paper describes acceptance and commissioning testing as verifying that a new system will perform as designed, and for a UPS the question is its ability to perform at differing power outputs and for how long.
| What happens | What is recorded |
|---|---|
| Site and drawing review before delivery | Clearances, ventilation, cabling and permit status |
| Placement, cabling and battery installation checked | Torque, polarity and installation checks |
| Start-up to the maker's procedure | Settings and start-up record |
| Functional tests of every mode and transfer | Each transfer and its result |
| Alarm and communication tests | Alarms received by the people who need them |
| Load test at the maker's steps | Readings at each step; any finding |
| Battery baseline readings | Per-block reference values |
| Handover | The handover file and the maintenance schedule |
Whoever the maker's warranty requires. Makers tie the warranty to an approved start-up: Eaton, for example, defines start-up of its 93PM and 9395 families as performed by an Eaton Customer Service Engineer or agent, and starts the parts warranty from that date. Read the warranty terms before booking the installation, and plan commissioning around the start-up, not instead of it. Electrical work also needs its permits: in Ontario, the Electrical Safety Authority says almost all electrical work requires a notification of work.
With the UPS output on a load bank before the critical load is connected, at the steps the maker's method sets; Eaton's UPS method runs 50% load for one hour and 100% for 3 hours, then a short battery discharge and repeated transfers. Some large UPS can test themselves: Vertiv's safe capacity test circulates power inside the Liebert Trinergy Cube and EXL S1 during start-up and commissioning, without an external load bank. New batteries need care before a discharge: C&D calls for a freshening charge and a float period before a load test within its stated window. Details in load bank testing.
We install and commission three-phase UPS for data centres, server rooms and industrial sites, working to each maker's procedures and with the site's electrical contractor. For sizing before you buy, see UPS sizing; for installation and start-up by brand, see UPS installation and services.
On some large UPS with a built-in test function, yes; otherwise a load bank is the way to prove the UPS at known load before it carries the critical load.
Usually. Makers tie the warranty to an approved start-up; check the terms for your model before the installation date.
Almost always for the electrical work. In Ontario, the Electrical Safety Authority requires a notification of work for almost all electrical work; other provinces have their own rules.
It depends on the size of the system and the tests in the method; a load test alone takes several hours.
Sources, checked 2026-10-04: